This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.
a. Paths would be 1,2,3,4 and 1,2,5
b. Path would be 1,2,3,4,5
c. Paths would be 1,2 and 3,4,5
d. Paths would be 1,2,3,5 and 1,2,4
Question 11 options:Paths would be 1,2 and 3,4,5Paths would be 1,2,3,5 and 1,2,4Path would be 1,2,3,4,5Paths would be 1,2,3,4 and 1,2,5
Question 12(1 point)At a minimum, network diagrams illustrate the ____ constraints among activities.
Get answer to your question and much more
Activities in a network diagram are drawn in a ____ relationship because, from a technical standpoint,they must be performed in that sequence.
Get answer to your question and much more
Question 14(1 point)Resource utilization charts based on each activity’s latest start time are said to be based on an ____schedule.
Get answer to your question and much more
Question 15(1 point)Resource utilization charts based on each activity’s earliest start time are said to be based on an ____schedule.Question 15 options:as-flexible-as-possible
as-late-as-possibleas-neededas-soon-as-possibleQuestion 16(1 point)____ is an iterative method in which resources are allocated to activities based on the least slack
Get answer to your question and much more
Question 17(1 point)In ____, when several activities need the same limited resource at the same time, the activities with theleast slack have first priority.Question 17 options:resource monitoringresource levelingresource limited schedulingresource evaluation schedulingQuestion 18(1 point)
The resource requirements plan illustrates
Get answer to your question and much more
SaveQuestion 19(1 point)Resources in a project are
Get answer to your question and much more
Question 20(1 point)Activities drawn in a serial relationship illustrate aQuestion 20 options:technical constraint among the activities.
loop format of scheduling the project.
Upload your study docs or become a
Course Hero member to access this document
Upload your study docs or become a
Course Hero member to access this document
End of preview. Want to read all 12 pages?
Upload your study docs or become a
Course Hero member to access this document