When several activities need the same limited resource at the same time which of the following activities have first priority?

This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.

a. Paths would be 1,2,3,4 and 1,2,5

b. Path would be 1,2,3,4,5

c. Paths would be 1,2 and 3,4,5

d. Paths would be 1,2,3,5 and 1,2,4

Question 11 options:Paths would be 1,2 and 3,4,5Paths would be 1,2,3,5 and 1,2,4Path would be 1,2,3,4,5Paths would be 1,2,3,4 and 1,2,5

Question 12(1 point)At a minimum, network diagrams illustrate the ____ constraints among activities.

Get answer to your question and much more

Activities in a network diagram are drawn in a ____ relationship because, from a technical standpoint,they must be performed in that sequence.

Get answer to your question and much more

Question 14(1 point)Resource utilization charts based on each activity’s latest start time are said to be based on an ____schedule.

Get answer to your question and much more

Question 15(1 point)Resource utilization charts based on each activity’s earliest start time are said to be based on an ____schedule.Question 15 options:as-flexible-as-possible

as-late-as-possibleas-neededas-soon-as-possibleQuestion 16(1 point)____ is an iterative method in which resources are allocated to activities based on the least slack

Get answer to your question and much more

Question 17(1 point)In ____, when several activities need the same limited resource at the same time, the activities with theleast slack have first priority.Question 17 options:resource monitoringresource levelingresource limited schedulingresource evaluation schedulingQuestion 18(1 point)

The resource requirements plan illustrates

Get answer to your question and much more

SaveQuestion 19(1 point)Resources in a project are

Get answer to your question and much more

Question 20(1 point)Activities drawn in a serial relationship illustrate aQuestion 20 options:technical constraint among the activities.

loop format of scheduling the project.

Upload your study docs or become a

Course Hero member to access this document

Upload your study docs or become a

Course Hero member to access this document

End of preview. Want to read all 12 pages?

Upload your study docs or become a

Course Hero member to access this document

Can constrain the project schedule because the quantities of various types of resources available to perform the project activities may be?

-Resources can constrain the project schedule because the quantities of various types of resources available to perform the project activities may be limited.

How does the delaying of activities affect the project?

The delaying of activities helps give others more time on their tasks because they won't affect the project schedule. It is good practice to have the person who will be responsible for the costs associated with the work make the cost estimates.

Why would activities be drawn in a serial relationship in a network diagram?

Network diagrams illustrate the technical constraints among activities. Activities are drawn in a serial relationship because, from a technical standpoint, they must be performed in that sequence.

How does the network logic also take into account resource constraints?

In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints? Activities that use the same resource may not be able to occur in parallel to each other. In resource-limited scheduling, the lower priority activities get delayed.